Home » NEWS » I-20 bridge work nears halfway point

I-20 bridge work nears halfway point

JACKSON — As construction crews work diligently to construct the I-20 westbound bridge over State Street/U.S. 51, 48 percent of the construction of the bridge has been completed and is on schedule, according to the Mississippi Department of Transportation (MDOT).

An average of 130,000 vehicles travel the I-20 area daily.

In July, crews began hanging steel girders on the project. Two spans of girders have been completed out of the five spans that will be installed on the project. The retaining wall west of the bridge has also been completed.

The I-20 Westbound Bridge was built in the 1960s. Once the new bridge is constructed it will meet current interstate standards and allow for future plans of the interstate system.

BEFORE YOU GO…

… we’d like to ask for your support. More people are reading the Mississippi Business Journal than ever before, but advertising revenues for all conventional media are falling fast. Unlike many, we do not use a pay wall, because we want to continue providing Mississippi’s most comprehensive business news each and every day. But that takes time, money and hard work. We do it because it is important to us … and equally important to you, if you value the flow of trustworthy news and information which have always kept America strong and free for more than 200 years.

If those who read our content will help fund it, we can continue to bring you the very best in news and information. Please consider joining us as a valued member, or if you prefer, make a one-time contribution.

Click for more info

About Wally Northway

Leave a Reply

Your email address will not be published. Required fields are marked *

*