Home » NEWS » Energy » TVA revises of cost of nuclear plant construction to $4.5B

TVA revises of cost of nuclear plant construction to $4.5B

NORTH MISSISSIPPI — The Tennessee Valley Authority says the revised total cost to complete Unit 2 at Watts Bar Nuclear Plant in Spring City, Tenn., is up to $4.5 billion.

The earlier estimate in 2007 had been $2.49 billion.

The federal utility, in a statement yesterday, blamed the increase on poor previous estimates and that reviews to support the initial estimate were not completed.

TVA also said the unit is now expected to be done between September and December 2015. The previous date was this year.

Unit 1 at the plant is already operating, along with three nuclear units at Browns Ferry in Alabama and two at Sequoyah near Chattanooga. The nuclear units generate about a third of TVA’s total power supply for the Tennessee Valley region.

BEFORE YOU GO…

… we’d like to ask for your support. More people are reading the Mississippi Business Journal than ever before, but advertising revenues for all conventional media are falling fast. Unlike many, we do not use a pay wall, because we want to continue providing Mississippi’s most comprehensive business news each and every day. But that takes time, money and hard work. We do it because it is important to us … and equally important to you, if you value the flow of trustworthy news and information which have always kept America strong and free for more than 200 years.

If those who read our content will help fund it, we can continue to bring you the very best in news and information. Please consider joining us as a valued member, or if you prefer, make a one-time contribution.

Click for more info

About Megan Wright

Leave a Reply

Your email address will not be published. Required fields are marked *

*