Home » NEWS » Energy » Grand Gulf refueling taking longer than expected

Grand Gulf refueling taking longer than expected

Grand Gulf Nuclear Station

VICKSBURG — Refueling Grand Gulf Nuclear Station has taken longer than plant officials said a year ago, and officials now aren’t saying when it will be completed.

The Claiborne County plant shut down Feb. 19 to refuel the boiling-water reactor and increase its generating capacity by 13 percent.

Entergy Nuclear spokeswoman Suzanne Anderson says that neither the time frame nor the outage duration could be discussed due to safety and security concerns. In April 2011, plant manager Jeremy Browning said the outage would last 75 days.

The $510 million upgrade was to last at least through June, when contracts run out for many of the 4,000 or so workers brought in for the work.

Once complete, Grand Gulf will be the nation’s most powerful single reactor.

BEFORE YOU GO…

… we’d like to ask for your support. More people are reading the Mississippi Business Journal than ever before, but advertising revenues for all conventional media are falling fast. Unlike many, we do not use a pay wall, because we want to continue providing Mississippi’s most comprehensive business news each and every day. But that takes time, money and hard work. We do it because it is important to us … and equally important to you, if you value the flow of trustworthy news and information which have always kept America strong and free for more than 200 years.

If those who read our content will help fund it, we can continue to bring you the very best in news and information. Please consider joining us as a valued member, or if you prefer, make a one-time contribution.

Click for more info

About Megan Wright

Leave a Reply

Your email address will not be published. Required fields are marked *

*