TUPELO — Renovations at the BancorpSouth Arena in Tupelo are going to take a little longer.

The arena is undergoing a $1.8 million project to repair, replace and paint the exterior insulation finishing system that covers the building.

Director Todd Hunt says workers found more water damage than expected, including a few rusted columns and metal studs, so more work must be done.

The Northeast Mississippi Daily Journal reports Hunt says the extra work totals $91,130 and will add 34 days to the completion date, which is now Sept. 19.

The arena will celebrate its 20th anniversary this fall, with a special concert season planned. So far, two concerts for this season have been announced: Backstreet Boys on Aug. 28 and John Fogerty on Oct. 22.

 — Northeast Mississippi Daily Journal

BEFORE YOU GO…

… we’d like to ask for your support. More people are reading the Mississippi Business Journal than ever before, but advertising revenues for all conventional media are falling fast. Unlike many, we do not use a pay wall, because we want to continue providing Mississippi’s most comprehensive business news each and every day. But that takes time, money and hard work. We do it because it is important to us … and equally important to you, if you value the flow of trustworthy news and information which have always kept America strong and free for more than 200 years.

If those who read our content will help fund it, we can continue to bring you the very best in news and information. Please consider joining us as a valued member, or if you prefer, make a one-time contribution.

Click for more info

About Megan Wright

Leave a Reply

Your email address will not be published. Required fields are marked *

*