Kemper County plant's costs continue to rise; completion delayed again

Kemper-Update-Logo_rgbKEMPER COUNTY — Southern Co. said yesterday that it will cost at least another $59 million to finish the power plant it’s building in eastern Mississippi’s Kemper County, pushing the total cost above $5.6 billion.

The Atlanta-based parent of Mississippi Power Co. also announced that the work on the parts of the plant that will gasify lignite and extract chemicals now won’t be done until the second half of 2015. Another part, where turbines generate electricity, is running on natural gas.

The additional money is supposed to pay for material and labor during the plant’s startup phase, including contract workers to help test equipment and systems. Last month, Southern increased the amount of money for these items by $29 million.

Mississippi Power said it, and not its 186,000 customers from Meridian to the Gulf Coast, will pay the additional money.

Customers are already paying 18 percent higher rates for Kemper. Mississippi Power has said it’s likely to seek an additional increase of at least 4 percent over 20 years to pay off $1 billion in bonds that the Legislature is allowing the company to issue as part of the settlement.

The plant and associated lignite coal mine were originally supposed to cost $2.8 billion.

The utility is on track to absorb $1.65 billion in cost overruns, as well as $133 million in federal tax credits that the company is forgoing. The latest overruns won’t officially be absorbed until Southern announces quarterly earnings on Oct. 29.

Spokesman Jeff Shepard said the company is constantly re-evaluating how much Kemper will cost.

“As decisions are made, the schedule gets pushed out and it’s decided additional costs are going to be required,” Shepard said yesterday in a telephone interview.

He was unable to provide further details on exactly why spending on the startup and testing phase is expanding so rapidly.

In August, Mississippi Power put three power generating turbines into commercial operation burning natural gas piped to the east Mississippi plant, even as Mississippi Power works complete parts of the plant that will turn lignite coal into synthetic gas. The entire operation, which Mississippi Power calls Plant Ratcliffe, is scheduled to be completed before the end of June 2015.

 

BEFORE YOU GO…

… we’d like to ask for your support. More people are reading the Mississippi Business Journal than ever before, but advertising revenues for all conventional media are falling fast. Unlike many, we do not use a pay wall, because we want to continue providing Mississippi’s most comprehensive business news each and every day. But that takes time, money and hard work. We do it because it is important to us … and equally important to you, if you value the flow of trustworthy news and information which have always kept America strong and free for more than 200 years.

If those who read our content will help fund it, we can continue to bring you the very best in news and information. Please consider joining us as a valued member, or if you prefer, make a one-time contribution.

Click for more info

About Megan Wright

Leave a Reply

Your email address will not be published. Required fields are marked *

*