Home » NEWS » Energy » Refund ordered for Kemper power customers

Refund ordered for Kemper power customers

Kemper-Update-Logo_rgbAssociated Press

Mississippi Power Co. has been ordered to refund its customers for a rate increase put into effect in 2013 to begin paying for Kemper County power plant it is building.

The Mississippi Supreme Court ordered the refund Thursday. In a 5-4 ruling, the Supreme Court said the state Public Service Commission erred in granting the increase.

The PSC approved in March of 2013 an immediate 15 percent increase followed by a 3 percent increase in 2014. Atlanta-based Southern Company said it could start paying off debt related to the Kemper plant.

The Kemper project has been plagued with cost overruns. Earlier this month, Southern Co. said it will spend at least another $45 million to finish the power plant, pushing total costs to nearly $6.2 billion.

BEFORE YOU GO…

… we’d like to ask for your support. More people are reading the Mississippi Business Journal than ever before, but advertising revenues for all conventional media are falling fast. Unlike many, we do not use a pay wall, because we want to continue providing Mississippi’s most comprehensive business news each and every day. But that takes time, money and hard work. We do it because it is important to us … and equally important to you, if you value the flow of trustworthy news and information which have always kept America strong and free for more than 200 years.

If those who read our content will help fund it, we can continue to bring you the very best in news and information. Please consider joining us as a valued member, or if you prefer, make a one-time contribution.

Click for more info

About Ross Reily

Ross Reily is editor of the Mississippi Business Journal. He is a husband to an amazing wife, dad to 3 crazy kids and 2 dogs. He is also a fan of the Delta State Fighting Okra and the Boston Red Sox.

Leave a Reply

Your email address will not be published. Required fields are marked *

*