Kemper County power plant costs rise another $30M

KEMPER COUNTY — Southern Co. says it will cost at least another $30 million to finish the power plant it’s building in eastern Mississippi’s Kemper County, pushing the total cost to nearly $5.6 billion. The Atlanta-based parent of Mississippi Power Co. said the additional money will pay for material and labor during the plant’s startup […] [...]

PSC delays Kemper power plant hearing; Blanton files motion

JACKSON  — The Mississippi Public Service Commission today delayed hearings on whether Mississippi Power Co. has spent prudently in building the $5.5 billion Kemper County power plant. Prudency hearings are a key step in the company collecting from its 186,000 ratepayers to pay for the plant, even though rates have already risen 18 percent. The […] [...]

Alabama Power closing two coal units, blames federal regulations

Alabama Power Co. says federal regulations are forcing it to close two coal-fired units at its Walker County power plant and to cease using coal at others, according to a story from the Birmingham Business Journal. The Birmingham-based utility said it will close two coal-fired units at Plant Gorgas in Walker County and work toward […] [...]

Mississippi Power conducts successful tests at Kemper plant

KEMPER COUNTY — Workers at Mississippi Power’s Kemper County energy facility successfully reached two major testing milestones: testing of the combined cycle unit and pressure testing of both gasifiers. The successful completion of the tests is an indication of continued progress on putting both pieces of equipment into service. Recent testing of the combined cycle […] [...]

EPA wants deep cut in state’s carbon emissions from power plants

WASHINGTON — The federal government is proposing that Mississippi’s carbon dioxide emissions from power plants be 38 percent lower by year 2030 compared to 2005. The U.S. Environmental Protection Agency announced specific targets for all states today as part of the Obama administration’s effort to reduce carbon dioxide emissions nationwide. Mississippi’s 2012 carbon emission rate […] [...]

Southern Co. moves startup date for Kemper County plant

KEMPER COUNTY — The Southern Co. says the expected startup date of its coal gas-fired power plant in Kemper County is being pushed back to the first half of 2015. In a regulatory filing yesterday with the Securities and Exchange Commission, the company also says the plant’s cost is expected to rise by $196 million […] [...]

Judge to rule on release of Kemper power plant data

KEMPER COUNTY — A judge will sort out which records about Mississippi Power Co.’s Kemper County power plant should be released to a group that opposes the plant. The Mississippi Supreme Court ruled Thursday that Hinds County Chancery Judge Dewayne Thomas should release information sought by the Bigger Pie Forum, while withholding other information about […] [...]

Southern Co.: Kemper plant construction cost could grow by $40M

KEMPER COUNTY — The Southern Co. says it may cost another $40 million to finish the $5-billion-plus power plant and mine it’s building in eastern Mississippi’s Kemper County. The Atlanta-based parent of Mississippi Power Co. said yesterday that it would set aside money in the plant’s budget to cover possible start-up problems. Critics have warned […] [...]

Power plant lands $181M loan from USDA

BATESVILLE — The U. S. Department of Agriculture is providing a loan for work at an electric power generation facility in Panola County. The federal agency Friday announced in a news release that it is providing $181 million to the South Mississippi Electric Power Association. The money will be used to purchase two natural gas-fired […] [...]

Price tag for Kemper plant grows by another $150M

KEMPER COUNTY — Mississippi Power Co. says the expected cost of the power plant it’s building in Kemper County has risen another $150 million because of schedule delays. That pushes the total cost of the plant, a coal mine and associated pipelines to almost $5 billion. The complex was originally projected to cost about $2.8 […] [...]

Next Page »

Recent Posts

Polls

How ready is your business for health care reform?

View Results

The MBJ poll should not be considered a scientific one. Results reflect only the opinion of those who participate.

Loading ... Loading ...

Recent Comments