The question of who should foot the bill for a new and controversial power plant is on hold. Upcoming hearings on whether Mississippi Power Co. should be able to get customers to pay for its Kemper County power plant have been postponed. The Mississippi Public Service Commission yesterday delayed prudency hearings from May 19 until […]

Continue reading...

Kemper plant costs revised upward again

April 2, 2014

0 Comments

kemper-update-logo-large_rgb-300x247

The cost of Mississippi Power’s controversial plant being built in Kemper County is rising again. The Southern Co. says it will cost at least another $177 million to finish the power plant it’s building in eastern Mississippi’s Kemper County, pushing the total cost above $5.2 billion The Atlanta-based parent of Mississippi Power Co. said yesterday […]

Continue reading...

Kemper plant overruns drag down Southern Co. earnings

October 30, 2013

0 Comments

Cost overruns in construction of Mississippi Power’s Kemper County lignite coal plant so far this year have taken a nearly $800 million bite out of parent Southern Co.’s earnings. A cooler than normal summer across the Southeast further eroded earnings, the company reported in its third quarter earnings statement. Frequent rainfall combined with what Southern […]